Panel titleBorder colorBackground colorTitle background colorTitle text color
In progress
#339860
#c8f3c8
whitegreen
Partial work completed#caceac#e0e5bdwhite#868c5b
Not Started#aaafaf#d7ddddwhiteblack
Completed#5e95a5#bddce5white#5e95a5


A Vision for Hyrax

Our common needs and experiences over the past few years have moved the Samvera Community in the direction of, for a great many of us, convergence on using Hyrax as a platform for our repository work. It is not possible or sustainable for Hyrax to be all things to all parties; the goal of Hyrax is to be an opinionated — though configurable — base for both institutional & data repositories and digital collections management repositories. Thus, we plan to continue building Hyrax in a way that allows it to be used off-the-shelf and as a springboard for highly customized solutions.

While improving daily, the current implementation of Hyrax is more suited to institutional & data repository use cases than it is to digital collections management repository use cases. Expected functionality for managing digital collections such as bulk ingest, edit, and export; database performance; and flexibility around collections and collection types are all noticeably missing from Hyrax. In order to realize the vision of Hyrax serving as a base for both sets of use cases, we propose focusing the upcoming release series on functionality for digital collections repositories while bolstering functionality for institutional & data repositories. (Most of the prioritized functionality will, we believe, be useful in both use cases.)

Development of new features is not our only goal for Hyrax. Feedback from the community is clear that there is a need to shift some of our focus to building more sustainable community practices around code maintenance, documentation, testing, and communication. While not entirely specific to Hyrax, we include suggested improvements in these areas as they will impact Hyrax development and the broader Samvera Community. As we progress in these areas, we will better articulate the resource needs and processes for the continued development of our shared software.

...

Targeted within the Next Year (from today)

Listed roughly in priority order and the expected order of implementation.  Some efforts may be implemented at the same time.  The priority order may shift as the year proceedsbased on available resources and community interest.


Accessibility modifications and enhancements

Address the backlog of accessibility issues in Hyrax and inform the testing process to include more robust and regular accessibility testing

Lead: Tom Johnson? (DCE
Panel
borderColor#339860
bgColor#c8f3c8
titleColorgreen
borderWidth1
titleBGColorwhite
borderStylesolid
titleIn progress
Target Date: Q3 2018
- [project board|https://github.com/samvera/hyrax/projects]

Bugfixes & Ongoing Maintenance Work

The Hyrax Maintenance Working Group is charged with supporting core maintenance and development for Hyrax in order to provide a stable base of support for the solution bundle.  This working group is not meant to be a replacement for community-led development efforts and/or contributions, but rather, it is meant to augment such efforts.  This group may work on some Roadmap Items.  When they do, the group will be identified in the Status Summary section of the item.

Status Summary/Major Activities:

  • July-December 2021 Cycle - Focus on issue clean-up, documentation, and testing Valkyrie work 
    • moving forward without Tech Lead, preparing for pledge-driven maintenance work in 2022

Target Date:
December 31, 2021

Lead: Juliet Hardesty
(Indiana University)
Working Group: 
Hyrax Maintenance Working Group

Status Summary/Major Activities:

  • January-June 2021 Cycle - Focus on issue clean-up in general
Target Date:
June 30, 2021
Lead: Juliet Hardesty
(Indiana University)
Working Group:
Hyrax Maintenance Working Group
Project Board
  • 2018-08-13 Focus of sprint focused on Accessibility roadmap item
Target Date: onging

Lead: tamsin johnson (UCSB)

Working Group: Hyrax Working Group
sprint





Swappable backends (i.e., Valkyrie support)

Target Date: TBD
Lead: Justin Coyne (Stanford University)
Working Group: Samvera Data Mapper Working Group

Description:
Panel
borderColor#caceac
bgColor#e0e5bd
titleColor#868c5b
borderWidth1
titleBGColorwhite
borderStylesolid
titlePartial work completed
- [milestone|https://github.com/samvera/hyrax/milestone/9]

Hyrax-Valkyrie

Minimum Viable Product (MVP) repository solution which enables the use of multiple disparate storage backends for both files and metadata using the Data the Data Mapper pattern.

Status Summary/Major Activities:

Target Date: March 11-April 5 (2, 2-week sprints)

Lead: tamsin woo (UCSB)

Working Group: Samvera Data Mapper Working Group



Bulk import/export

Target Date: TBD
Lead: TBD
Working Group: TBD

Description:
Panel
borderColor#aaafaf#c8f3c8
bgColor#c8f3c8
titleColor#d7ddddgreen
borderWidth1
titleBGColorwhite
borderStylesolid
titleNot started
In Progress - [milestone|https://github.com/samvera/hyrax/milestone/14]

Batch RoundTripping of Data (import, export, edit)

2021-01-12 - This is almost done and could be considered for inclusion in Hyrax or as an add-on/gem option. Might have feature flipper that doesn't install gem unless it is configured. Might also have this installed but not turned on without a configuration setting.

Allow bulk ingest and export of content and/or metadata from Hyrax using both command line and user interfaces.

Status Summary/Major Activities:

Panel
borderColor#caceac
bgColor#e0e5bd
titleColor#868c5b
borderWidth1
titleBGColorwhite
borderStylesolid
titlePartial work completed

Analytics , reporting, and related notifications

  • community effort planning for early 2018 - Lead: Steve Van Tuyl (Oregon State University)

  • Hyrax Analytics Working Group (HAWG)
  • Phase One WG outputs
  • Coordination of focus and scope with representatives from Batch WG, Avalon, Hyrax, and Hyku (completed Late 2018)
  • Oregon Digital is creating an RFP to fund the development of this feature set
Target Date: Summer 2021

Lead: Rob Kaufman (Notch8 via Oregon State)

Working Group:
This work is related to, but not entirely encompassed by, Hyrax Batch Import-Export WG
Issues



#5e95a5
Panel
borderColor#caceac
bgColor#e0e5bd
titleColor#868c5b
borderWidth1
titleBGColorwhite
borderStylesolid
titlePartial work completed
Panel
borderColor#5e95a5
bgColor#bddce5
titleColor

Group and responsibility management

re

2021-01-12 - Being worked on in Hyku

Re-architect groups and responsibilities to improve clarity of function

- Lead: LaRita Robinson (University of Notre Dame) Samvera Permissioning Analysis and Design Working Group

.

Status Summary/Major Activities:

Panel
borderColor#aaafaf
bgColor#d7dddd
borderWidth1
titleBGColorwhite
borderStylesolid
titleNot started

Enhanced batch edit interface

  • build out batch edit functionality to meet the needs, specifically, of digital collections-based repository implementations (UI mock-ups are available) - Lead: Undefined

Completed in the Last Year (from today)

  • Hyrax Bridge Development Effort - the goal of this effort is to implement some new permission features for Hyrax in the near term, while the Permissioning Analysis Working Group completes it's pilot phase.
Target Date: Spring 2019

Working Group:

NA (though see Permissioning Analysis Working Group above)

Project Board





...

Current Roadmap

Anchor
Proposed
Proposed
Proposed/Beyond One Year

Completed

Proposed or Future (more than a year out)

Enhancement Requests (in Issues)


HTML Comment
hiddentrue

Colors to use with panels to show status...

Panel titleBorder colorBackground colorTitle background colorTitle text color
Proposed
#303d4d
#e5eef9
white#303d4d
More than a year out#303d4d#e5eef9white#303d4d



Collection Extensions Working Groups Collection Extensions
  • A set of functionality to expand how collections work.  It includes collection types which control what a collection can do, nesting, branding, control of discovery, control of multiple membership, etc.  Completed Q2 of 2018 and released in Hyrax 2.1 - Lead: Lynette Rayle (Cornell University) 

  • Panel
    borderColor#303d4d
    bgColor#e5eef9
    titleColor#303d4d
    borderWidth1
    titleBGColorwhite
    borderStylesolid
    titleCompleted
    Proposed

    Replace Actor Stack with DRY Transactions

    Use DRY Transactions instead of the actor stack to make process clearer and easier to back out when things go wrong.

    Status Summary/Major Activities:

    • TBA


    Target Date: TBD

    Lead: tamsin johnson(DCE)

    Working Group: TBD




    panel
    Panel
    borderColor#5e95a5#aaafaf
    bgColor#bddce5#d7dddd
    titleColor#5e95a5black
    borderWidth1
    titleBGColorwhite
    borderStylesolid
    titleCompletedProposed
    Implementing remaining

    UI

    mockups
    • address the backlog of UI mockups in Hyrax and Hyku and backport any Hyku UI features that are valuable in Hyrax (ongoing since late 2017) - Lead: Aaron Collier and Justin Coyne (Stanford University)

    Future (more than a year out)

    Rectification

    Project to resolve UI-related issues in Hyrax.

    Status Summary/Major Activities:

    • Proposed (DRAFT) Project Board
    • Coordinating among Hyrax Product Owner, UX Interest Group, and Repository Managers Interest Group
    Target Date: TBDWorking Group:Project Board