NOTE: Original name was Collections Development Sprints (aka Display Sets). All references to Display Sets in these documents can be replaced with the term Collection Extensions.
Phases:RequirementsUI/UX DesignDevelopment Sprints

Charter:

Scope & Objectives

This group will expand the current User Collections implementation to meet the requirements set forth in the Collection Extensions Requirements Working Group (aka Display Sets Working Group).  The work will follow mockups currently under development by the by Collection Extensions UI/UX Design Working Group.




This group will primarily be comprised of core and UI developers with support from UI/UX designers.  Members need to be able to commit to the following deliverables and timeframe.

Deliverables & Timeframe

Deliverables will include:

  • Creation of issues for the implementation
  • Implementation of Milestones 1 & 2 + Collection Types from Milestone 3  (see Requirements - Display Sets)

This group will have a virtual and in person component.  The virtual sprints are expected to begin August 7, 2017.  A one week in-person sprint hosted at University of Michigan is scheduled for August 21-25.  We hope to complete all work for the Collection extensions implementation within the 6-week sprint period. You do NOT have to participate in both the virtual and in-person sprints to be a part of the implementation team.

Sprint Timetable

DateLocationPlanned Focus1
July
  • Sprint planning:
    • github issues
    • sprint milestones
    • resource planning
    • communication planning
week 1: August 7-11
week 2: August 14-18
Virtual
Virtual
  • Low hanging fruit
  • Infrastructure for core features
week 3: August 21-25
week 4: August 28 - September 1
In-Person
Virtual
  • Core complex features

week 5: September 5-8
week 6: September 11-15

Virtual
Virtual
  • Completion of complex features
  • Remaining loose ends

1 The planned focus will become better defined as we get closer to the sprint dates.

Meeting Times & Communication Channels

  • The exact nature of the virtual sprints is TBD.

  • Logistics information for the in-person is TBD.


Slack channel:  https://project-hydra.slack.com/messages/collection_extensions/

Meeting Notes


Members

Note that to be a member of a Working Group, you must have have a CLA in place if you are committing code and you must consent to release documentation under a  Creative Commons Attribution-Share Alike 3.0 Unported License .

Putting your name on this list expresses general interest.  We will firm up commitments as the date for the sprint process draws nearer.  Sprint dates are expected to be three 2-week sprints with the first sprint beginning Aug 7 - Sept 15.

Facilitator : Lynette Rayle (Cornell)  