The ArcLight Phase II work cycle is a focused, nine week effort (August 13-October 11, 2019) to refine the usability and accessibility of the ArcLight MVP, to address strategic needs in a community-based fashion, and to improve maintainability. Like the design process and MVP work, this work cycle is a community-based project. For broader context, please review the inception deck (link TK).
Timeline and milestones:
- August 13th: Kick-off Meeting (10AM PT)
- October 11th: End of Workcycle
- October 9th-11th: Blacklight Summit at Duke
- ??? :Community Report-out
Meeting schedule and communication channels
Schedule TK. Unless otherwise noted, all meetings are held on Zoom: https://stanford.zoom.us/j/777354887
The primary communication channels for the work cycle across contributors are the #arclight
channel on Code4lib Slack and the arclight-2019-workcycle email list. Communication with the community will be via the arclight-community Google Group.
Links
- GitHub repository
- Project board
- Google Drive folder (Inception deck, Work cycle plan/running notes)