new deliverables and timeframes are in place on wiki; old ones are archived on a separate page so they still exist
Fedora release is out
HMWG sprint hasn’t focused on Sirenia - this will be Hyrax 5.1 release; to get there we need CI testing set up completed (switch over to Github Actions); add Sirenia tests to that and away we go
Hyrax 5.1 will be fixing significant bugs for Sirenia and fix pair-tree change from Fedora update
no timeframe for 5.1 yet, analytics work happening first/in parallel (if we have resources available)
before Daniel’s tech lead time is done (July 1)
Next HMWG sprint starts April 15
migration and Emory - Emily reports building out prod instance of H5 F6; setting up work type and configs and bring over local customization for pres metadata (fixity checking, virus scanning); using S3 with F6; migrating collection from F3, doing export using F tools then bring in to Hyrax through Bulkrax; testing Bulkrax soon; found new bugs and reported with tickets (Circle CI with F6 on Samvera-orb)
10:30am - 10:50am
Nurax set up
Performance Testing
10:50am - 11:00am
Wrap Up
Next meeting proposal:
April 26th @ 11am Eastern
Establish regular meetings 4th Friday of each month at 9 am Eastern?